Window Repair & Replacement
Example project description
“Three windows in the living room have failed seals — the glass is foggy between the panes. One window in the bedroom has a cracked frame and does not close properly. We want to replace all four windows.”
Project Overview
Replace four windows: three double-pane units with failed seals (fogged glass) in the living room, and one window with a damaged frame and compromised closure in the bedroom. All units to be replaced with new energy-efficient double-pane windows matching existing rough opening dimensions.
Scope of Work
- 1Measure all four existing window rough openings and confirm new unit sizes
- 2Order replacement windows (allow 1–2 week lead time for custom sizes)
- 3Remove interior and exterior trim on all four windows — set aside reusable pieces
- 4Remove existing window units from rough openings — dispose of old units
- 5Inspect rough openings for rot, moisture damage, or structural issues — repair as found
- 6Install new window units per manufacturer specifications — shim and level
- 7Apply continuous bead of low-expansion foam around perimeter (interior)
- 8Apply flashing tape and exterior sealant at all seams and head flashing
- 9Reinstall or replace interior and exterior trim
- 10Paint or caulk trim to match existing finish
- 11Test all windows for smooth operation, full closure, and locking function
Materials Required
- Replacement windows (4 units, allowance for standard double-hung) — ~$280/unit (~$1,120)
- Low-expansion foam — 2 cans — ~$18
- Flashing tape — 1 roll — ~$22
- Exterior caulk — 2 tubes — ~$16
- Trim lumber (if replacement needed) — ~$60
- Paint / primer — ~$35
- **Materials subtotal (with 12% overage): ~$1,430**
Labor Requirements
- Trade: Carpenter / window installer
- Crew: 2 workers
- Estimated hours: 8–10 hours
- **Labor subtotal (with 25% overhead): ~$750**
- --
Estimated Project Cost
| Ballpark Estimate | |
|---|---|
| Materials | $1,430 |
| Labor | $750 |
| TOTAL | $2,180 |
⚠️ Ballpark estimate. Final cost depends on window brand, size, and any rot or structural repair found during installation.
Site Safety Requirements
- Secure openings immediately if windows are removed in advance of install date
- Wear gloves when handling glass — inspect for cracks before removal
- Ladder safety required for any second-floor work
Cleanup & Disposal
- Remove and dispose of all old window units
- Vacuum all debris from interior sill areas
- Wipe down all new windows and hardware before handoff
Warranty Expectations
- Window manufacturer warranty: typically 10–20 years on glass seal, 1–5 years on hardware
- Installation workmanship: 1 year
© 2026 TAGS — The Apartment Guys System. All rights reserved.
Generated by TAGS · tagyourproject.com
Get a custom scope for your actual project
Upload photos and describe your repair. TAGS generates a professional SOW tailored to your specific project — in under 60 seconds.
Property managers: 3 free SOWs to start. Homeowners: $20 per scope.